Post Preparing an Acumen Risk Analysis Schedule

A reliable Deltek Acumen Schedule Risk Analysis (SRA) has three pillars, and the first and most important one is a well-built schedule.

An accurate SRA has three components: a quality schedule, well-defined duration/cost uncertainty, and discrete risk events. Again, the most crucial element is a quality schedule. It is not worth proceeding with the SRA if the schedule is lacking. Read More [url]https://tensix.com/2020/12/preparing-an-acumen-risk-analysis-schedule/[/url]
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Quantitative Schedule Risk Analysis - A Valuable Risk Tool For A Project Team Emily Project Management 1 12-22-2023 12:07 AM
Deltek Acumen Schedule: Cost Uncertainty and Cost Risk Emily Other Tools 0 02-18-2019 08:54 AM
Cost vs Schedule Risk Analysis for Proposals Emily Project Management 0 11-13-2015 08:57 AM
Review: Full Monte Schedule Risk Analysis for Microsoft Project Emily Microsoft 0 02-07-2012 08:20 AM
Schedule Risk Analysis: What Is It and Why Do It? Emily Scheduling 1 02-03-2012 04:53 AM


All times are GMT -5. The time now is 11:56 PM.


Powered by: vBulletin - Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2009, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.