Post Deltek Acumen and Schedule Contingency

So, you want to know how many days contingency on your deterministic schedule are required to achieve a completion date on your risk adjusted schedule, at an 80% confidence level. Deltek Acumen histogram plots provide the completion dates and associated confidence levels of risk adjusted schedules http://ed.gr/b56o2
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Deltek Acumen Schedule: Cost Uncertainty and Cost Risk Emily Other Tools 0 02-18-2019 07:54 AM
Using Deltek Acumen Fuse’s Trend Analysis Emily Other Tools 0 09-28-2018 06:52 AM
Why Using Deltek Acumen for Schedule Analytics is Recommended Emily Scheduling 0 01-18-2018 07:20 AM
Video: Deltek Acumen Fuse Diagnostics In Action Emily Scheduling 0 09-13-2017 07:59 AM
Deltek Acumen Fuse Schedule Diagnostics Emily Other Tools 0 06-27-2017 11:19 AM


All times are GMT -5. The time now is 01:33 PM.


Powered by: vBulletin - Copyright ©2000 - 2020, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2009, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.