Project Management Knowledge Base

Go Back   Project Management Knowledge Base > Peer Support > Primavera Systems

Reply
 
LinkBack Thread Tools Display Modes
  #1  
Old 05-27-2009, 10:11 PM
Forum Newbie
 
Join Date: May 2009
Posts: 7
Revised Base Line Schedule

Hi All,

I am a civil Engineer and now use Primavera (P5) software in deep for Project Management. But I learnt through self studies. I want to share your valuable knowledge.

I want to know about base line schedule. I have made already a cost loaded base line schedule. After I update it I want to revise the Base Line Schedule.
Please tell me anyone whether I want to reschedule the updated schedule (with actual) or update the maintained base line schedule according to the Schedule Management.

Priyangi
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Useful techniques to fine-tune your project schedule projectmanager Scheduling 2 11-06-2010 08:39 PM
Useful Techniques to Fine-Tune Your Project Schedule ExecutiveBrief Scheduling 3 11-06-2010 07:21 PM
Schedule Contingency Rob Green Scheduling 15 11-06-2010 07:04 PM
MicroSoft Project Schedule Integration Issue.. Apollo14 Scheduling 1 06-03-2008 11:50 AM
Free sample of a custom home schedule template pmkb Templates / Files 0 10-13-2005 09:37 AM


All times are GMT -5. The time now is 08:04 AM.


Powered by: vBulletin - Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2009, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.