Post Primavera P6 - Float on Critical Activities?

One of our customers recently encountered the perplexing situation whereby total float was greater than zero on some of their critical activities in Primavera P6. Here's how [URL="http://ow.ly/S1Pr30cfV3l"]http://ow.ly/S1Pr30cfV3l[/URL]
Reply With Quote
  #2  
Old 06-07-2017, 06:59 AM
Project Hobbyist
 
Join Date: Oct 2016
Posts: 50
Thumbs up Primavera P6 activities

1. Project Calendar
2. Resource Calendar
3. Task dependent activity
4. Resource dependent activity.
To know more about the activities & how to manage those activities learn from [URL="https://proventuresindia.com/oracle-primavera-p6"]experts.[/URL]
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Marking Near Critical Activities in Primavera P6’s Activities Table Emily Primavera Systems 0 08-26-2016 06:02 AM
Primavera P6 EPPM – Reporting on Critical & Near Critical Activities Emily Primavera Systems 0 05-01-2015 05:40 AM
Primavera P6 – Displaying Total Float of Activities on the Gantt Chart Emily Primavera Systems 0 03-25-2015 07:25 AM
Monitoring Near Critical Activities in Primavera P6 Emily Primavera Systems 0 11-10-2014 09:22 AM
AACE 29R-03 is flawed: davilara Scheduling 1 05-31-2011 11:21 AM


All times are GMT -5. The time now is 06:04 PM.


Powered by: vBulletin - Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2009, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.