Primavera etc/actual hours problem This is a project which was already created when I got here, all I am doing is changing the ETC in accordance with the PMs directions, but when I do, the actuals this period keep going up!! Can anyone tell me what would cause this? It almost seems like its balancing out?? Thanks for any help :-) |
#2
| |||
| |||
Have you tried store period performance? my suggestion is that before you do an update: make a back-up, do store period performance, then update the programme to the next data date.. hope this helps... |