P6 won't spread stored period performance

I'm having trouble getting P6 to spread stored period performance over time. I have the box checked for "link actual to date and actual this period units and cost" I have created the financial periods. When I enter an actual it merely adds it to the first weeks total. I am fairly new at using stored period performance so any help would be appreciated.
Reply With Quote
  #2  
Old 01-26-2016, 04:03 PM
Forum Newbie
 
Join Date: Jan 2016
Location: Naperville, Illinois
Posts: 2
Found something out

I found out that the schedule data date needed to be moved before the actuals could be input into the specific week. Now, however when I input a specific period performance, p6 spread the actuals over the weeks. Why won't p6 apply actuals to the specific stored period?
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
3 things you should know about personality and project manager performance Ben-PM Project Management 0 08-22-2013 09:32 AM
Product vs Process WBS for performance measurements louarnold Planning 0 02-18-2013 10:40 AM


All times are GMT -5. The time now is 02:22 PM.


Powered by: vBulletin - Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2009, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.