Post How to Exclude Relationships on Baseline Bars in Primavera P6

When a project is first baselined & progress has been entered, relationship arrows will connect to the baseline bars instead of the current schedule bars. Here's how to change that so that they connect to the schedule bars in Primavera P6 [url]http://ed.gr/cn9lc[/url]
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
A Quick Way to Remove All Relationships from a Primavera P6 Schedule Emily Primavera Systems 0 01-22-2020 09:42 AM
Removing All Schedule Activity Relationships ‘the Cool Way’ in Primavera P6 Emily Primavera Systems 0 12-11-2017 09:16 AM
Primavera P6 and the Bars Label Mystery Emily Primavera Systems 0 11-24-2017 08:21 AM
Removing Relationships from Multiple Activities in Primavera P6 Emily Primavera Systems 1 10-17-2016 01:50 AM
Showing Relationship Arrows between Schedule Activity Bars and Not Baseline Bars Emily Primavera Systems 0 12-02-2014 09:51 AM


All times are GMT -5. The time now is 10:46 PM.


Powered by: vBulletin - Copyright ©2000 - 2025, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2009, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.