Earned value chart I have calculated the following information: BAC for 6 month project: $500,000 • PV = $250,000 • EV = $230,000 • AC = $300,000 Cost variance is $-70,000 Schedule variance is $-20,000 Cost performance index is 0.76 Schedule performance index is 0.92 Estimate at completion for this project is $657,895 |