#1
| |||
| |||
update p3 schedule I am new planner and I want to ask a question about primavera if any one have answer please advice me. The question is when I want to update p3 some activity actually not started as in target plan so I have to change both start and finish. how can I make this revise because when I change it manually the od ( original duration) changes automatically and I don’t want to change OD . The question simply how I can update schedule using primavera p3. Please if any planner have detailed answer just tell me I really appreciate that. I am so happy to be here |
#2
| ||||
| ||||
Are you using retained logic?
__________________ "I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team |
#3
| |||
| |||
thanks and i need clarification sorry i dont understand you what you means by retained logic . i am new primavera user thanks and best regards Alaa Alhaj |
#4
| ||||
| ||||
[url=http://www.pmicos.org/topics/aug2003.asp]retained logic vs. progress override[/url]
__________________ "I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team |
#5
| |||
| |||
... You never change the start or finish of a task unless it's started and/or finished actually. You can change the remaining (or original) durations of the task or its predecessors so as to move the start or finish date (after you reschedule [F9]), but the whole concept of a scheduling program is that you tell it what and how long, it tells you when. |
#6
| |||
| |||
Thanks Thank you very much Mr jim Shaffer Best Regards ALAA ALHAJ |
#7
| |||
| |||
hi every body. vI am very new to use Primavera. We are using P3 for scheduling. I have been given a work to update the project after making Target2 (baseline2) because the Target1 already exists. I want to then update plan and compare it with the baseline. What necessary reference document I will be needed to update my plan and to know about the actual progress. What will be the steps to complete this update? What reports I have to check after updating the plan and how I can get these reports. Manually I am updating activity actual start and planned date and percentage by using the activity form. And then I schedule it. Should I add some columns in the current plan for target 1 and 2 to compare? In short I want to know the procedure. Best Regards M. Usman |
#8
| |||
| |||
alaaalhaj From my experience you should never update the Target plan manually coz there is a big chance of error in doing this, if you decide to do this then you have to be more cautious. One thing you can do is to export the Base cuve into excel (weekly or monthly), then this becomes your planned percentage to compare with your actual. Hope this helps.. |
Thread Tools | |
Display Modes | |
| |
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Main use of schedule | pmkb | Project Management | 15 | 11-24-2023 09:08 AM |
Schedule Contingency | Rob Green | Scheduling | 15 | 11-06-2010 07:04 PM |
Free sample of a custom home schedule template | pmkb | Templates / Files | 0 | 10-13-2005 09:37 AM |