update p3 schedule

Hi every body

I am new planner and I want to ask a question about primavera if any one have answer please advice me.

The question is when I want to update p3 some activity actually not started as in target plan so I have to change both start and finish. how can I make this revise because when I change it manually the od ( original duration) changes automatically and I don’t want to change OD . The question simply how I can update schedule using primavera p3. Please if any planner have detailed answer just tell me I really appreciate that.

I am so happy to be here
Reply With Quote
  #2  
Old 06-24-2007, 09:44 AM
pmkb's Avatar
Administrator
 
Join Date: Aug 2005
Location: Cyberspace
Posts: 326
Are you using retained logic?
__________________
"I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team
Reply With Quote
  #3  
Old 06-25-2007, 02:19 AM
Forum Newbie
 
Join Date: Jun 2007
Posts: 19
thanks and i need clarification

sorry i dont understand you what you means by retained logic . i am new primavera user

thanks and best regards
Alaa Alhaj
Reply With Quote
  #4  
Old 06-25-2007, 04:39 AM
pmkb's Avatar
Administrator
 
Join Date: Aug 2005
Location: Cyberspace
Posts: 326
[url=http://www.pmicos.org/topics/aug2003.asp]retained logic vs. progress override[/url]
__________________
"I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team
Reply With Quote
  #5  
Old 09-10-2007, 07:21 AM
Forum Newbie
 
Join Date: Jun 2007
Location: Indianapolis, IN USA
Posts: 6
Quote from alaaalhaj View Post:
Hi every body

I am new planner and I want to ask a question about primavera if any one have answer please advice me.

The question is when I want to update p3 some activity actually not started as in target plan so I have to change both start and finish. how can I make this revise because when I change it manually the od ( original duration) changes automatically and I don’t want to change OD . The question simply how I can update schedule using primavera p3. Please if any planner have detailed answer just tell me I really appreciate that.

I am so happy to be here
... Don't update your target... It's fixed in time. It's a target. You can't hit a moving target....

... You never change the start or finish of a task unless it's started and/or finished actually. You can change the remaining (or original) durations of the task or its predecessors so as to move the start or finish date (after you reschedule [F9]), but the whole concept of a scheduling program is that you tell it what and how long, it tells you when.
Reply With Quote
  #6  
Old 09-11-2007, 02:58 AM
Forum Newbie
 
Join Date: Jun 2007
Posts: 19
Thumbs up Thanks

Thank you very much
Mr jim Shaffer


Best Regards
ALAA ALHAJ
Reply With Quote
  #7  
Old 03-02-2009, 09:09 AM
Forum Newbie
 
Join Date: Mar 2009
Posts: 1
hi every body.

vI am very new to use Primavera. We are using P3 for scheduling. I have been given a work to update the project after making Target2 (baseline2) because the Target1 already exists. I want to then update plan and compare it with the baseline. What necessary reference document I will be needed to update my plan and to know about the actual progress. What will be the steps to complete this update? What reports I have to check after updating the plan and how I can get these reports.
Manually I am updating activity actual start and planned date and percentage by using the activity form. And then I schedule it. Should I add some columns in the current plan for target 1 and 2 to compare? In short I want to know the procedure.

Best Regards
M. Usman
Reply With Quote
  #8  
Old 03-05-2009, 04:42 AM
Project Hobbyist
 
Join Date: Dec 2005
Location: Muscat
Posts: 71
Send a message via Yahoo to cdevera
alaaalhaj

From my experience you should never update the Target plan manually coz there is a big chance of error in doing this, if you decide to do this then you have to be more cautious. One thing you can do is to export the Base cuve into excel (weekly or monthly), then this becomes your planned percentage to compare with your actual.

Hope this helps..
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Main use of schedule pmkb Project Management 15 11-24-2023 09:08 AM
Schedule Contingency Rob Green Scheduling 15 11-06-2010 07:04 PM
Free sample of a custom home schedule template pmkb Templates / Files 0 10-13-2005 09:37 AM


All times are GMT -5. The time now is 08:27 PM.


Powered by: vBulletin - Copyright ©2000 - 2024, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2009, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.