![]() | Advertise on this site |
|
#1
| |||
| |||
| Hi every body I am new planner and I want to ask a question about primavera if any one have answer please advice me. The question is when I want to update p3 some activity actually not started as in target plan so I have to change both start and finish. how can I make this revise because when I change it manually the od ( original duration) changes automatically and I don’t want to change OD . The question simply how I can update schedule using primavera p3. Please if any planner have detailed answer just tell me I really appreciate that. I am so happy to be here |
|
#2
| ||||
| ||||
| Are you using retained logic?
__________________ "I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team Do you have experience using project management software? Write a review! |
|
#3
| |||
| |||
| sorry i dont understand you what you means by retained logic . i am new primavera user thanks and best regards Alaa Alhaj |
|
#4
| ||||
| ||||
|
__________________ "I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team Do you have experience using project management software? Write a review! |
|
#5
| |||
| |||
... You never change the start or finish of a task unless it's started and/or finished actually. You can change the remaining (or original) durations of the task or its predecessors so as to move the start or finish date (after you reschedule [F9]), but the whole concept of a scheduling program is that you tell it what and how long, it tells you when. |
|
#6
| |||
| |||
| Thank you very much Mr jim Shaffer Best Regards ALAA ALHAJ |
| Thread Tools | |
| Display Modes | |
|
|
| | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Schedule Contingency | Rob Green | Scheduling | 12 | 05-23-2008 10:00 AM |
| Main use of schedule | pmkb | Project Management | 8 | 12-13-2007 06:35 AM |
| Free sample of a custom home schedule template | pmkb | Templates / Files | 0 | 10-13-2005 08:37 AM |