Project Management Knowledge Base
Advertise on this site

Go Back   Project Management Knowledge Base > Peer Support > Primavera Systems
Home Project Management Forum Software and Book Reviews Project Management News Register Mark Forums Read


Reply
 
LinkBack Thread Tools Display Modes
  #1  
Old 06-24-2007, 07:41 AM
Forum Newbie
 
Join Date: Jun 2007
Posts: 19
Default update p3 schedule

Hi every body

I am new planner and I want to ask a question about primavera if any one have answer please advice me.

The question is when I want to update p3 some activity actually not started as in target plan so I have to change both start and finish. how can I make this revise because when I change it manually the od ( original duration) changes automatically and I don’t want to change OD . The question simply how I can update schedule using primavera p3. Please if any planner have detailed answer just tell me I really appreciate that.

I am so happy to be here
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #2  
Old 06-24-2007, 09:44 AM
pmkb's Avatar
Administrator
 
Join Date: Aug 2005
Location: Cyberspace
Posts: 249
Default

Are you using retained logic?
__________________
"I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team

Do you have experience using project management software? Write a review!
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #3  
Old 06-25-2007, 02:19 AM
Forum Newbie
 
Join Date: Jun 2007
Posts: 19
Default thanks and i need clarification

sorry i dont understand you what you means by retained logic . i am new primavera user

thanks and best regards
Alaa Alhaj
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #4  
Old 06-25-2007, 04:39 AM
pmkb's Avatar
Administrator
 
Join Date: Aug 2005
Location: Cyberspace
Posts: 249
Default

retained logic vs. progress override
__________________
"I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team

Do you have experience using project management software? Write a review!
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #5  
Old 09-10-2007, 07:21 AM
Forum Newbie
 
Join Date: Jun 2007
Location: Indianapolis, IN USA
Posts: 6
Default

Quote from alaaalhaj View Post:
Hi every body

I am new planner and I want to ask a question about primavera if any one have answer please advice me.

The question is when I want to update p3 some activity actually not started as in target plan so I have to change both start and finish. how can I make this revise because when I change it manually the od ( original duration) changes automatically and I don’t want to change OD . The question simply how I can update schedule using primavera p3. Please if any planner have detailed answer just tell me I really appreciate that.

I am so happy to be here
... Don't update your target... It's fixed in time. It's a target. You can't hit a moving target....

... You never change the start or finish of a task unless it's started and/or finished actually. You can change the remaining (or original) durations of the task or its predecessors so as to move the start or finish date (after you reschedule [F9]), but the whole concept of a scheduling program is that you tell it what and how long, it tells you when.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #6  
Old 09-11-2007, 02:58 AM
Forum Newbie
 
Join Date: Jun 2007
Posts: 19
Thumbs up Thanks

Thank you very much
Mr jim Shaffer


Best Regards
ALAA ALHAJ
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
Schedule Contingency Rob Green Scheduling 12 05-23-2008 10:00 AM
Main use of schedule pmkb Project Management 8 12-13-2007 06:35 AM
Free sample of a custom home schedule template pmkb Templates / Files 0 10-13-2005 08:37 AM


All times are GMT -6. The time now is 05:02 PM.


Powered by: vBulletin - Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2008, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.