I am beginner coming from using MS Project. How to I set my project to auto adjust the start date based on the task's predecessor? I have a time constraint on my projects finish date. I would like to be able to adjust my durations and then have Primavera adjust the next tasks start date based on the predecessors. Is this not a good idea? It is exhausting to enter in all of the start dates, early start, late start, for every task. What am I missing here? I am guessing that I am just missing something simple here. Thanks for the help ahead of time...