How to import Expected finish date It would be a great help if someone would tell me how to import the Expected finish date in P6 using Excel import. I actualized the start of an activity through actual start date and tried to change the Expected finish date the same way....but the activity got actualized but didnt get the expected finish date . Plz help |
#2
| |||
| |||
Expected Finish My workaround is to import the expected finish date to a user defined date field and then use global change to get it into the expected finish date. |
Thread Tools | |
Display Modes | |
| |
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Oracle Primavera P6 Must Finish By Date Explained | Emily | Primavera Systems | 1 | 02-02-2012 02:19 AM |
example of a finish to finish relationship | joegoe | Planning | 0 | 10-20-2011 06:28 AM |
Focus date vs actual date | sanlen | Scheduling | 0 | 02-25-2010 01:41 AM |
P3 - How to auto adjust task start date based on predecessor? | wazzubrad | Primavera Systems | 2 | 06-26-2009 02:45 PM |
schedule problem | milan27 | Primavera Systems | 6 | 04-17-2009 12:03 PM |