Old 11-16-2006, 01:15 PM
Forum Newbie
 
Join Date: Nov 2006
Posts: 2
Default Scheduling issues with 150+ tasks

I have a project schedule with 160 tasks with 6 resources assigned against them. When there is a change in the duration due to actual work hours the plan adjusts itself since it has predecessors linked properly with no danglers.
The resources have been assigned as per their availability and as an when they come out of other tasks.

During the course of the project a new resource joins and I need to accomodate him into the tasks plus I have the need to shuffle resources based on their performance on prior tasks (complexity, skills etc...)

When I try to do this, I need to re-look and re-adjust the entire plan to re-assign the predecessor links. It is so difficult,time consuming and tedious to do it. What I currently do is to filter by the resource names and re-set the predecesor links. But what I am not sure is if my resources are allocated in the most optimal manner as I had done it when I prepared the schedule the first time with a lot of thought process.

I use Microsoft project for scheduling. I would like to know about better and smarter ways to handle a schedule that is highly dynamic.

This is my first post and thanks in advance for all your help.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #2  
Old 11-17-2006, 10:20 AM
pmkb's Avatar
Administrator
 
Join Date: Aug 2005
Location: Cyberspace
Posts: 255
Default

It sounds like you are adding predecessors/successors for soft logic. It's something that most (all?) scheduling programs do not address well IMO. In classic CPM theory/practice, relationships should only represent real or necessary (hard) constraints between tasks.
__________________
"I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team

Do you have experience using project management software? Write a review!
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #3  
Old 11-17-2006, 11:28 AM
Forum Newbie
 
Join Date: Nov 2006
Posts: 2
Default

Thanks pmkb for your response. Appreciate it. Would be nice if you could you ellaborate on it a little more. I did not quite understand your point. Thanks.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #4  
Old 11-20-2006, 07:56 AM
pmkb's Avatar
Administrator
 
Join Date: Aug 2005
Location: Cyberspace
Posts: 255
Default

Soft logic represents relationships that are added to a CPM network to reflect a desired plan of execution, but not necessarily a true constraint. For example, tying a string of similar tasks FS because one resource/crew will be assigned to the work (whereas it may be possible - though not planned - to assign more resources and work the tasks in parallel or work them in a different order/sequence).

Hard logic represent relationships that represent real, unavoidable constraints. For example, you have to open the tube of toothpaste before you can extrude toothpaste onto your toothbrush.

In general, schedules that contain a lot of soft logic will require a lot of editing when project execution invariably deviates from the plan.
__________________
"I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team

Do you have experience using project management software? Write a review!
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #5  
Old 03-03-2007, 12:26 AM
pepkoRn's Avatar
Forum Newbie
 
Join Date: Mar 2007
Location: Pasig City, Philippines
Posts: 4
Thumbs up Structure know-how

if you're the one who built the structure of the schedule then basically you know how to get into its branching. I still try to configure til now (4 months) the P3 schedule turned-over to me by our previous planner and the technique i have encounter, maybe a little answer to your problem is to identify the critical path or the major activities where the rest is connected. Try understanding the structure as one-line item only, then connect everybody to that single line. Experiment.
__________________
pepkoRn
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On
Forum Jump

Similar Threads
Thread Thread Starter Forum Replies Last Post
scheduling constraints???? francismoyalan Planning 5 03-03-2007 12:32 AM
Practice Standard for Scheduling pmkb Scheduling 3 08-24-2006 05:47 AM
Dissertation papers on planning and scheduling pmkb Planning 4 08-24-2006 05:45 AM
scheduling algorithms barthelemy Scheduling 2 01-25-2006 06:52 AM


All times are GMT -6. The time now is 04:52 PM.


Powered by: vBulletin - Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2008, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.