Project Management Knowledge Base
Advertise on this site

Go Back   Project Management Knowledge Base > Project Management Knowledge Base > Scheduling
Home Project Management Forum Software and Book Reviews Project Management News Register Mark Forums Read


Reply
 
LinkBack Thread Tools Display Modes
  #11  
Old 05-10-2006, 10:54 AM
Forum Newbie
 
Join Date: May 2006
Location: Stevenson, WA
Posts: 5
Default

In almost all cases, even when I don't use this contingency task at the end of the schedule, I develop my projects so that there is some float in the longest chain. I try to have a cushion between the last task in the schedule and the contractual finish date.

A rule of thumb that I have used is to have a minimum of 5 days of Total Float for every 12 months of project duration. Thus a two year long project has at least 10 days of TF. In EPC type projects with multiple entities I try to double this figure as a week of time can be lost quite quickly. I try to be careful and not acheive this extra float by being overly optimistic in activity durations or the use of flaky logic techniques.

I have experimented a couple of times with having this buffer at the end of each major phase of a project (Eng'g, Procurement, Construction, Commissioning), and it seems to work well. I still need to formalize the rules for draw down and communication so that it is more transparent to all of the parties involved. At the moment it is more of a planner/schedulers technique than a project management practice.
__________________
Tony Bolstad
Planner
Scheduling and Information Services, Inc.
www.1sis.com
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #12  
Old 05-20-2008, 01:06 PM
Forum Newbie
 
Join Date: May 2008
Posts: 1
Default Schedule Contingency - Part Deux



I would like to revitalize this discussion and hear opinions of the application and use of Schedule Contingency (Not Total Float) in a formal EVMS environment.

Given the following scenario....
  • Project Schedule has been developed and resourced loaded and scrubbed to a five year duration, with a scheduled completion date of Dec 08 (for sake of discussion).
  • A probabilistic risk analysis is conducted using PertMaster that identifies a need for 3 months of schedule contingency.
  • Based upon the risk assessment, the contract completion date is agreed upon of March 09.
There are two equally compelling schools of thought as to how this should be reflected in the project schedule and the Performance Baseline (PMB).

The first approach is that schedule contingency should be included in the project schedule and PMB by the addition of "Contingency" activities tied to various key interim milestones such as the completion of Preliminary Design etc. or by setting a "must finish" constraint on the completion milestone and generating a total float equal to the contingency. Either of these approaches would have the effect of generating earned value performance relative to the contract completion date, however there is no structured control over the use contingency during project execution.

The second approach would be to establish the project baseline based upon the original schedule and hold the schedule contingency offline, (not included in the PMB). Inclusion of the schedule contingency into the baseline would be controlled through change control in the same manner as cost contingency. Thus the difference between the "Schedule Completion Date" and the "Contract Completion Date" would equal the schedule contingency in the same way as the difference between the PMB and "Contract Budget Base" equals the Cost Contingency.

This is a hot topic in the DOE as performance against both schedule and contract completion dates are typically a metric that drives incentive fees and/or liquidated damages. The first approach tends to favor the contractor, while the second approach is more consistent with EVMS criteria that excludes contingency and management reserve from performance measurement.

Would appreciate any thoughts or opinions from others.
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
  #13  
Old 05-23-2008, 10:00 AM
pmkb's Avatar
Administrator
 
Join Date: Aug 2005
Location: Cyberspace
Posts: 255
Default

I prefer the second approach as it helps keep the team members who are using the schedule as the basis for setting priorities in directing the effort focused on the right goalposts.
__________________
"I love it when a plan comes together." - Colonel John "Hannibal" Smith, A-Team

Do you have experience using project management software? Write a review!
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
Reply


Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On
Forum Jump


All times are GMT -6. The time now is 04:53 PM.


Powered by: vBulletin - Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2008, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.