Default Activity on node help

Hi, I have just started a basic construction qualification and im starting to learn the basics of project scheduling. I have been given an assignment to create a Gantt chart, activity on arrow diagram and find the CPA aswell as noting the earliest and latest start times.

I have been given the following information and have typed this into ms project and created a Gantt chart. You can see from the chart that tasks D,E and G have no proceeding activities and the Gantt chart shows that the latest finishing time for these 3 task is the last week of the project (week 49) this bit I understand but its when I get to the arrow on node diagram that I get confused. You can see in pic 1 I have 3 dummy arrow which are the 3 task with no preceding activities, according to the gantt chart these can finish on week 49 so ive typed week 49 ( nodes 5,6 and 8) is this correct???? The other way ive done (pic2) is to change the finish time to the nearest node, however on nodes 6 and 8 ive had to use a node which is a few in advance so there isnít negative slack. However doing it this way the 3 taskís donít have a latest finish time of 49 weeks like the Gantt chart shows?????

I hope this makes sense. Im sorry if it doesnít, but im very new to this.

Could some one please explain if im doing it right and if so, which diagram is correct regarding the slack.
Brian

Activity Description Duration (Wkís) Preceding tasks
A Outline Design 4 None
B Cost Estimates 2 A
C Client Review 2 B
D Planning Application 8 C
E Site Investigation 2 C
F Detailed Plans 4 C
G Building Regulations 6 F
H Tendering 4 F
I Client Approval 1 H
J Construction 30 I
K Fitting Out 1 J
L Client Hand Over 1 K
Attached Files
File Type: pdf pic2.pdf (60.1 KB, 8 views)
File Type: pdf pic1.pdf (60.1 KB, 6 views)
File Type: pdf Gannt chart question A.pdf (124.1 KB, 10 views)
Digg this Post!Add Post to del.icio.usBookmark Post in TechnoratiNetscape this post!Stumble this Post!
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Can not import activity code xls files michael.powell-brett Primavera Systems 0 02-17-2011 04:03 AM
Project Planning & activity based costing rahulved Planning 4 10-30-2010 08:27 AM
Reduce duration BGNS Project Management 1 10-02-2010 06:30 PM
Suretrak Formatting Activity Relationships Dannyboy Primavera Systems 0 09-18-2009 01:09 PM
Activity Graph - Calculation solomon_13000 Scheduling 1 03-17-2007 09:19 AM


All times are GMT -5. The time now is 09:17 PM.


Powered by: vBulletin - Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Content Relevant URLs by vBSEO ©2009, Crawlability, Inc.
Copyright (c) 2005 Measuring Up. All rights reserved.